Gravicon Project Lifecycle
The project is implemented through four consecutive stages, covering analysis, engineering, manufacturing, installation, as well as final commissioning. This step-by-step approach allows GRAVICON to control quality at every phase and deliver a fully operational processing plant.
Timeline
Click a phase to expand
Research
Engineering
Manufacturing
Commissioning
Research & Analysis
2 steps
2 week
W1–2
1
Providing a Representative Sample
1w
2
Study of a Representative Sample for Beneficiability
1w
Engineering and Contract Finalization
5 steps
11 weeks
W3–13
1
Preparation of Technical Requirements
1w
2
Preparation of Technical Assignments
1w
3
Coordination of Technical Specifications
1w
4
Conclusion of a Contract
2w
5
Design and Engineering Work
6w
Manufacturing and Logistics
1 steps
12 weeks
W14–24
1
Manufacturing and Supply of a Complete Set of Equipment
12w
Installation and Commissioning
5 steps
13 weeks
W25–38
1
Installation
8w
2
Installation Supervision
1w
3
Adjustment
2w
4
Staff Training
1w
5
Commissioning
1w